Wimmera Mallee Contracting Pty Ltd

Wimmera Mallee Contracting Pty Ltd Electrical Inspection Services Western Victoria

WMC Pty Ltd run by Quinn Mclean since 2020 G class LEI with 13 plus years, Covering Switch Boards, Temp Perm, CT Metered supply, Solar cogeneration, Stand a loan & Generator connections in the Wimmera Mallee Region

Lot and lots of battery’s done in the last few months
10/05/2026

Lot and lots of battery’s done in the last few months

Big Solar big day at work huge private system
09/05/2026

Big Solar big day at work huge private system

08/05/2026

Interesting solution

07/05/2026
06/05/2026

⚡COMPLIANCE ALERT: generating sets⚡

Let's jump right in!

1. Fault current availability.

The gen-set, depending on its size, may or may not have adequate fault current to trip protective devices under short circuit conditions. As per clause 2.6.2 of AS/NZS 3010:2017, all outgoing circuits must be protected against short circuit - unless you meet the exception to the above clause.

The easiest way is to measure the resistance of the consumer mains all the way through the windings of the gen-set. In other words:
1. Ensure the gen-set is OFF
2. Close all isolating switches on the gen-set
3. Measure the resistance between phases, and from phases to neutral, at the main switchboard
4. Measure the resistance of the protective earthing conductor from the main switchboard to the gen-set frame.

The resistance values obtained can then be plugged into Ohm's Law to determine the prospective fault current available for both phase-to-phase and phase-to-neutral faults, as well as phase-to-earth faults.

The resultant current value should be no less than the instantaneous tripping current of the protective device at the origin of the consumer mains at the gen-set. For example:

1. Your highest loop resistance measurement (say using the protective earthing conductor) is 0.3ohms
2. As per ohm's law, the lowest available fault current is 230/0.3=~765A
3. Your gen-set overcurrent device is a B63 circuit breaker, which has an instantaneous tripping current of 63*4=252A
4. Therefore, the consumer mains are protected against short circuit.

You can also re-test this live using an EFLI tester, or an NST.

You _can_ also calculate the prospective fault current available if provided with the internal impedance of the gen-set (e.g. 10%) using the following formula:

PFC=(S*100)/(693*Z)

Where S is the VA of the generator and Z is the internal impedance of the gen-set as a percentage. 693 is for three-phase gen-sets.

But my recommendation? Measure the resistances dead, and retest live using an EFLI tester or NST.

2. Neutral switching.

IF the gen-set is the sole supply to the electrical installation, you SHALL NOT switch the neutral at the gen-set isolating device (2.6.3 exception 2). Otherwise, you MUST switch the neutral at the gen-set.

The first scenario almost always applies when gen-sets are used to supply construction sites prior to grid supply availability.

In alternative or supplementary supply situations, the following applies:
1. The gen-set isolator MUST switch the neutral
2. Where hard-wired, the changeover device and main switch should not switch the gen-set neutral
3. Where plug-in, the changeover device MUST switch the gen-set neutral.

Thankfully, AS/NZS 3010:2017 has clear and useful figures to explain the various connection scenarios.

And remember: in all cases, gen-sets and their supplies are prescribed work and require inspection.

Got any questions? Ring Text or Email .

☀️ SOLAR INSPECTIONS: what is the inspector looking at? ☀️The law states the inspector must inspect _all_ of the prescri...
06/05/2026

☀️ SOLAR INSPECTIONS: what is the inspector looking at? ☀️

The law states the inspector must inspect _all_ of the prescribed work to determine if it complies. With solar installations being markedly more complex than a standard switchboard, the electrician and inspector need to get everything right.

Here's roughly how I go about it:

1. Documentation. I need it _all_ before I set foot on site, exactly as 4777.1 and 5033 stipulate. Then I'm checking:
* Wind certificate for mounting frame and clamping zones of PV modules
* Inverter installation requirements, like space around the inverter for ventilation and external earthing requirements
* Data sheets, site map accuracy, voltage rise calculations, etc.
* Voc and Isc calculations against inverter specs

An inspector cannot effectively carry out an accurate inspection if all key documentation is not present.

On site, next up is:
2. Visual inspection of inverter and relevant switchboards, including labelling. Then a visual inspection of all other components, starting in the roof space. I'll be checking for the appropriate signage, installation location of DC wiring systems, gluing and labelling of all conduits, anchoring of flexible conduits at both ends, appropriate support, etc.

I'm also checking that the AC inverter cable is installed correctly, particularly regarding mechanical protection if concealed in a stud wall.

3. Then we jump onto the roof. I'm verifying:
* PV modules and mounting frame are installed in accordance with the documentation (as per 1170.2), checking clamping zones, feet spacing and correct installation, and ensuring no PV modules are installed on rail overhangs
* Protection against corrosion of earthing terminations, and size of all conductors
* Support of wiring systems with steel ties, and water ingress countermeasures

4. Testing!
* While on the roof, verify earth continuity of mounting frames and modules
* Verify earthing to inverter and any other relevant parts
* IR test DC and AC cables
* Polarity test DC and AC cables, including continuity of DC strings
* Test DC isolator operation under load, and verify disconnection within 2s and reconnection after 60s.

I'll lastly verify correct regional settings (Australia A) and that the earth fault alarm has been set up for the customer on their smart device.

There's lots to it, but that's broadly it! A thorough inspection is not only the law, it protects the customer from danger and the electrician from a 'show cause' after an audit.

Generation and storage inspections were taken away from General-class inspectors and remade into a specialist RE class, recognising the particular dangers of such systems and the necessity of getting it right.

As as LGREV class inspector, I take my obligations seriously and strive to protect both the customer and the electrician from the ramifications of non-compliant work.

Morning
29/03/2026

Morning

23/03/2026

Its taken some time but have completed my V class Electrical inspectors licence LGREV

Little drive around Lake Tyrrell Sea Lake
22/03/2026

Little drive around Lake Tyrrell Sea Lake

Top of Mt William to connect the other Comms Tower but no luck
12/03/2026

Top of Mt William to connect the other Comms Tower but no luck

Address

3 Stawell Road
Horsham, VIC
3400

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 1pm
Thursday 8:30am - 4:30pm
Friday 8am - 12pm

Telephone

+61417556878

Website

Alerts

Be the first to know and let us send you an email when Wimmera Mallee Contracting Pty Ltd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Wimmera Mallee Contracting Pty Ltd:

Share